Status: announced · Confidence: medium · Announced: 2023-09
Facts
| Operator | Amazon Web Services (hyperscaler) |
|---|---|
| Location | Kentucky Springs Rd at Haley Dr (adjacent to North Anna Nuclear Power Station), Louisa, Louisa, VA |
| Building area | 1700000 sq ft |
| Buildings | 7 |
| Land | 153 acres |
| First recorded | 2026-07-05 |
| Last updated | 2026-07-05 |
Signal notes
One of the two campuses in AWS's ~$11B Louisa County Technology Overlay District program (announced August 2023, per Data Center Frontier); the per-campus investment split is not disclosed, so no investment_usd is recorded here. Construction milestones not verified in fetched sources — status kept as announced at medium confidence. Distinct from the larger North Creek Technology Campus (aws-north-creek-louisa) and from the withdrawn third Louisa campus (aws-louisa-third-campus).
Sources
- Amazon files for 3.8 million sq ft data center campus in Louisa County, Virginia — Data Center Dynamics, 2024-11-05
Location (Kentucky Springs Rd / North Anna Nuclear) and 1.7M sq ft / up to 7 buildings, filed Sept 2023. - AWS withdraws plans for third data center campus in Louisa County, Virginia — Data Center Dynamics, 2025-07-28
153 acres.
Signals
Raw observations behind this record (3):
sig-20260705-aws-lakeanna-land-acres,
sig-20260705-aws-lakeanna-location,
sig-20260705-aws-lakeanna-sqft
Record file · dataset licensed CC BY 4.0 — see provenance.