33 project-sites tracked. Each record is resolved from clustered, per-source signals — see the datasets for license and provenance.
By status
announced (14)
| site | operator | location | MW |
|---|---|---|---|
| Lake Anna Technology Campus (AWS) | aws | Louisa, VA | — |
| North Creek Technology Campus (AWS) | aws | Louisa, VA | — |
| DC BLOX Azalea Data Center | dc-blox | Henrico, VA | 10 |
| Digital Drive Campus (former Cartograf site) | chirisa | Chesterfield, VA | 300 |
| Google Project Loch | Chesterfield, VA | — | |
| Google Project Peanut | Chesterfield, VA | — | |
| Google Project Skye | Chesterfield, VA | — | |
| Iron Mountain Richmond Campus | iron-mountain | Henrico, VA | 200 |
| Microsoft Lakeside Commerce Park Campus | microsoft | Mecklenburg, VA | — |
| Microsoft Six-Building Mecklenburg Campus (2023 filing) | microsoft | Mecklenburg, VA | — |
| Microsoft Tunstall Road Campus | microsoft | Mecklenburg, VA | — |
| QTS RIC4/RIC5 Expansion | qts | Henrico, VA | — |
| Tuckahoe Technology Park | tract | Goochland, VA | 900 |
| Iron Horse Business Park data center campus | westdulles | Hanover, VA | — |
permitted (3)
| site | operator | location | MW |
|---|---|---|---|
| Province Group Data Center Campus (Page Road) | province-group | Powhatan, VA | 300 |
| Hanover Technology Park | tract | Hanover, VA | 2400 |
| White Oak Technology Park 2 (Hourigan Rezoning) | hourigan | Henrico, VA | — |
under-construction (3)
| site | operator | location | MW |
|---|---|---|---|
| Hyperion (Richland Parish Data Center) | meta | Richland Parish, LA | 2000 |
| Stargate Abilene (Lancium Clean Campus) | openai | Taylor, TX | 1200 |
| Vantage Ashburn I (VA1) Campus | vantage | Loudoun, VA | 206 |
operational (10)
| site | operator | location | MW |
|---|---|---|---|
| Project Rainier (New Carlisle campus) | aws | St. Joseph, IN | 2200 |
| Chirisa Technology Parks Richmond Campus (CTP-01/02/03) | chirisa | Chesterfield, VA | — |
| CloudHQ LC Campus (Ashburn) | cloudhq | Loudoun, VA | 160 |
| Google Council Bluffs data center campus | Pottawattamie, IA | — | |
| Iron Mountain Manassas Campus | iron-mountain | Prince William, VA | — |
| Meta Henrico Data Center | meta | Henrico, VA | — |
| Microsoft Boydton Campus | microsoft | Mecklenburg, VA | — |
| Fairwater (Mount Pleasant campus) | microsoft | Racine, WI | — |
| QTS Richmond Campus (White Oak Technology Park) | qts | Henrico, VA | — |
| Colossus / Colossus 2 | xai | Shelby, TN | 946 |
cancelled (3)
| site | operator | location | MW |
|---|---|---|---|
| AWS Third Louisa County Campus (Northeast Creek Reservoir) | aws | Louisa, VA | — |
| Hunting Hawk Technology Park | hhhunt | Hanover, VA | 900 |
| Mountain Road Technology Park | tract | Hanover, VA | — |
By state
IA (1)
- Google Council Bluffs data center campus — Pottawattamie · operational
IN (1)
- Project Rainier (New Carlisle campus) — St. Joseph · operational
LA (1)
- Hyperion (Richland Parish Data Center) — Richland Parish · under-construction
TN (1)
- Colossus / Colossus 2 — Shelby · operational
TX (1)
- Stargate Abilene (Lancium Clean Campus) — Taylor · under-construction
VA (27)
- Lake Anna Technology Campus (AWS) — Louisa · announced
- AWS Third Louisa County Campus (Northeast Creek Reservoir) — Louisa · cancelled
- North Creek Technology Campus (AWS) — Louisa · announced
- Chirisa Technology Parks Richmond Campus (CTP-01/02/03) — Chesterfield · operational
- CloudHQ LC Campus (Ashburn) — Loudoun · operational
- DC BLOX Azalea Data Center — Henrico · announced
- Digital Drive Campus (former Cartograf site) — Chesterfield · announced
- Google Project Loch — Chesterfield · announced
- Google Project Peanut — Chesterfield · announced
- Google Project Skye — Chesterfield · announced
- Hunting Hawk Technology Park — Hanover · cancelled
- Iron Mountain Richmond Campus — Henrico · announced
- Iron Mountain Manassas Campus — Prince William · operational
- Meta Henrico Data Center — Henrico · operational
- Microsoft Boydton Campus — Mecklenburg · operational
- Microsoft Lakeside Commerce Park Campus — Mecklenburg · announced
- Microsoft Six-Building Mecklenburg Campus (2023 filing) — Mecklenburg · announced
- Microsoft Tunstall Road Campus — Mecklenburg · announced
- Province Group Data Center Campus (Page Road) — Powhatan · permitted
- QTS RIC4/RIC5 Expansion — Henrico · announced
- QTS Richmond Campus (White Oak Technology Park) — Henrico · operational
- Tuckahoe Technology Park — Goochland · announced
- Hanover Technology Park — Hanover · permitted
- Mountain Road Technology Park — Hanover · cancelled
- Vantage Ashburn I (VA1) Campus — Loudoun · under-construction
- Iron Horse Business Park data center campus — Hanover · announced
- White Oak Technology Park 2 (Hourigan Rezoning) — Henrico · permitted
WI (1)
- Fairwater (Mount Pleasant campus) — Racine · operational
By operator
(7)
- Hunting Hawk Technology Park — VA · cancelled
- Province Group Data Center Campus (Page Road) — VA · permitted
- Tuckahoe Technology Park — VA · announced
- Hanover Technology Park — VA · permitted
- Mountain Road Technology Park — VA · cancelled
- Iron Horse Business Park data center campus — VA · announced
- White Oak Technology Park 2 (Hourigan Rezoning) — VA · permitted
aws (4)
- Lake Anna Technology Campus (AWS) — VA · announced
- AWS Third Louisa County Campus (Northeast Creek Reservoir) — VA · cancelled
- Project Rainier (New Carlisle campus) — IN · operational
- North Creek Technology Campus (AWS) — VA · announced
chirisa (2)
- Chirisa Technology Parks Richmond Campus (CTP-01/02/03) — VA · operational
- Digital Drive Campus (former Cartograf site) — VA · announced
cloudhq (1)
- CloudHQ LC Campus (Ashburn) — VA · operational
dc-blox (1)
- DC BLOX Azalea Data Center — VA · announced
google (4)
- Google Council Bluffs data center campus — IA · operational
- Google Project Loch — VA · announced
- Google Project Peanut — VA · announced
- Google Project Skye — VA · announced
iron-mountain (2)
- Iron Mountain Richmond Campus — VA · announced
- Iron Mountain Manassas Campus — VA · operational
meta (2)
- Meta Henrico Data Center — VA · operational
- Hyperion (Richland Parish Data Center) — LA · under-construction
microsoft (5)
- Microsoft Boydton Campus — VA · operational
- Microsoft Lakeside Commerce Park Campus — VA · announced
- Microsoft Six-Building Mecklenburg Campus (2023 filing) — VA · announced
- Fairwater (Mount Pleasant campus) — WI · operational
- Microsoft Tunstall Road Campus — VA · announced
openai (1)
- Stargate Abilene (Lancium Clean Campus) — TX · under-construction
qts (2)
- QTS RIC4/RIC5 Expansion — VA · announced
- QTS Richmond Campus (White Oak Technology Park) — VA · operational
vantage (1)
- Vantage Ashburn I (VA1) Campus — VA · under-construction
xai (1)
- Colossus / Colossus 2 — TN · operational