Sites / GA / Douglas
DataBank Atlanta campus (Lithia Springs)
Status: announced · Confidence: medium
Facts
| Location | Lithia Springs, Douglas, GA |
|---|---|
| Capacity | 120 MW |
| Land | 95 acres |
| First recorded | 2026-07-07 |
| Last updated | 2026-07-07 |
Signal notes
Operator "DataBank" needs an operators.yml entry — no id available, so operator field is omitted. Capacity resolved to 120MW critical IT load; source also cites a 180MW on-site Georgia Power substation (utility supply, not critical IT). Land ~95 acres near Lithia Springs. Source status "development (acquired Oct 2023)" mapped to announced — land acquired, no construction confirmed. Single good source (DCD).
Sources
- DataBank acquires 100 acres in Atlanta, Georgia for 120MW data center campus — DatacenterDynamics, 2026-07-06
Signals
Raw observations behind this record (3):
sig-20260706-databank-atlanta-capacity,
sig-20260706-databank-atlanta-land,
sig-20260706-databank-atlanta-status
Record file · dataset licensed CC BY 4.0 — see provenance.