Sites / WY / Laramie
Meta Cheyenne Data Center
Status: under-construction · Confidence: medium · Announced: 2024-07-08
Facts
| Operator | Meta (hyperscaler) |
|---|---|
| Location | Cheyenne, Laramie, WY |
| Building area | 715000 sq ft |
| Land | 960 acres |
| Investment | $800000000 |
| First recorded | 2026-07-07 |
| Last updated | 2026-07-07 |
Signal notes
Land acreage conflict: Wyoming Public Media (announcement-date, local primary) reports 960 acres in the High Plains Business Park; DataCenter Dynamics reports a 945-acre development. Resolved to 960 (announcement source) with the 945 minority claim preserved here; neither is disambiguated by an operator/government figure. investment_usd recorded as 800000000 but source says "more than $800 million" — treat as a floor. Status signal reads "announced/under construction (July 2024)"; resolved to under-construction with that ambiguity noted. Most facts rest on a single source (WPM), hence medium confidence.
Sources
- Meta announces $800 million data center in Cheyenne — Wyoming Public Media, 2024-07-08
Announcement; 960-acre parcel in High Plains Business Park, 715,000 sq ft, >$800M, LEED Gold targeted, Meta's 21st U.S. data center. - Meta named as company behind 945-acre data center development in Cheyenne, Wyoming — DataCenter Dynamics
Reports 945-acre development (conflicts with WPM's 960).
Signals
Raw observations behind this record (5):
sig-20260706-meta-cheyenne-acres-dcd,
sig-20260706-meta-cheyenne-acres-wpm,
sig-20260706-meta-cheyenne-investment,
sig-20260706-meta-cheyenne-sqft,
sig-20260706-meta-cheyenne-status