| Operator | Meta (hyperscaler) |
|---|---|
| Location | Eagle Mountain, Utah County, UT |
| Building area | 4500000 sq ft |
| Land | 193 acres |
| Investment | $1500000000 |
| First recorded | 2026-07-07 |
| Last updated | 2026-07-07 |
Signal notes
Multi-phase campus: reported operational and expanding, with the 193-acre campus set for completion in 2026 (4.5M sq ft at full build). investment_usd 1500000000 recorded as "over $1.5 billion" total after expansion. Building sqft and investment from Grist; land acreage from Utah News Dispatch.
Sources
- https://utahnewsdispatch.com/2026/04/17/eagle-mountain-193-acre-data-center-campus-is-set-to-be-done-this-year-with-big-water-promises/ — Utah News Dispatch, 2026-04-17
193-acre campus set for completion in 2026, with water-conservation commitments - https://grist.org/technology/utah-data-center-water-supply-meta-novva/ — Grist
operational and expanding; 4.5M sq ft once complete; expansion raises total investment to over $1.5B
Signals
Raw observations behind this record (4):
sig-20260706-meta-eagle-mountain-acres,
sig-20260706-meta-eagle-mountain-investment,
sig-20260706-meta-eagle-mountain-sqft,
sig-20260706-meta-eagle-mountain-status
Record file · dataset licensed CC BY 4.0 — see provenance.