Meta Prometheus (New Albany campus)
Status: under-construction · Confidence: medium · Operational: 2025-09
Facts
| Operator | Meta (hyperscaler) |
|---|---|
| Location | New Albany, Licking, OH |
| Capacity | 1000 MW |
| Land | 447 acres |
| First recorded | 2026-07-07 |
| Last updated | 2026-07-07 |
Signal notes
Meta's "Prometheus" AI supercluster at the New Albany campus. capacity_mw 1000 from NBC4i's "~1 GW" (approximate; basis unspecified). A separate DCD signal reports a 200 MW on-site gas power plant approved to serve the site — that is generation capacity, not IT load, so it is NOT resolved into capacity_mw and is recorded here for context only. land_acres 447 from "more than 447 acres" (a floor, not exact). operational_date reflects "first cluster in service September 2025"; status is under construction / partially operational with expansion continuing through 2026.
Sources
- Meet Prometheus, world's highest-capacity data center slated to open in Ohio in 2026 — NBC4i (WCMH), 2026-07-06
- Ohio regulators approve construction of 200MW gas power plant to serve Meta data center in New Albany, Ohio — Data Center Dynamics, 2026-07-06
200 MW on-site gas generation, not IT/data-center load
Signals
Raw observations behind this record (6):
sig-20260706-meta-prometheus-capacity,
sig-20260706-meta-prometheus-gas-plant,
sig-20260706-meta-prometheus-land-acres,
sig-20260706-meta-prometheus-operational-date,
sig-20260706-meta-prometheus-operator,
sig-20260706-meta-prometheus-status