Sites / VA / Prince William
Prince William Digital Gateway
Status: cancelled · Confidence: medium
Facts
| Developer | QTS Data Centers |
|---|---|
| Location | Prince William, VA |
| Building area | 23000000 sq ft |
| Land | 2100 acres |
| First recorded | 2026-07-09 |
| Last updated | 2026-07-10 |
Signal notes
Cancelled: the project officially died when developer QTS Data Centers withdrew its petition on July 2. A 23M-sq-ft complex planned on 2,100 acres near Manassas National Battlefield Park. Distinct site from the Dulles South Innovation Center. Negative outcome recorded per KB-0001. New signals (2026-07-10) re-confirm land (2,100 acres), building_sqft (23M, now carried in its own signal), and withdrawn/cancelled status from the same Virginia Business source.
Sources
- Prince William supervisors reject another big data center project — Virginia Business, 2026-07-08
Signals
Raw observations behind this record (5):
sig-20260709-pw-digital-gateway-land,
sig-20260709-pw-digital-gateway-status,
sig-20260710-pw-digital-gateway-building-sqft,
sig-20260710-pw-digital-gateway-land-acres,
sig-20260710-pw-digital-gateway-status
Record file · dataset licensed CC BY 4.0 — see provenance.